濟南輕型鋼結(jié)構(gòu)是由鋼板、熱軋型鋼和冷加工成型的薄壁型鋼制造而成,在廠房、機場或者火車站的設計施工中鋼結(jié)構(gòu)已經(jīng)是較為主流的選擇之一。鋼結(jié)構(gòu)工程施工時間短并且外形裝飾效果佳,今天小編就為大家簡單的介紹一下濟南輕型鋼結(jié)構(gòu)工程的優(yōu)缺點以及施工的流程及注意事項
Jinan light steel structure is made of steel plate, hot-rolled section steel and cold-formed thin-walled section steel. Steel structure has been one of the more mainstream choices in the design and construction of plant, airport or railway station. The construction time of steel structure engineering is short and the appearance decoration effect is good. Today, Xiaobian will briefly introduce the advantages and disadvantages of Jinan steel structure engineering, as well as the construction process and precautions
1、鋼結(jié)構(gòu)施工前應組織監(jiān)理人員、施工單位技術(shù)人員對設計圖紙和有關(guān)技術(shù)標準進行會審。
1. Before the construction of steel structure, the supervisor and the technical personnel of the construction unit shall be organized to jointly review the design drawings and relevant technical standards.
 
2、鋼結(jié)構(gòu)構(gòu)件進場驗收,確保其質(zhì)量符合設計要求。
2. Steel structure members shall be accepted on site to ensure that their quality meets the design requirements.
 
3、根據(jù)設計要求對地基進行預埋地腳螺栓連接、混凝土澆筑。
3. The foundation shall be connected with embedded anchor bolts and poured with concrete according to the design requirements.
 
4、現(xiàn)場吊裝,遵循先柱后梁,先下后上,從中間到兩邊的吊裝原則。
4. On site hoisting shall follow the principle of column before beam, down before up, and from the middle to both sides.
 
5、對吊裝結(jié)構(gòu)進行校正,用吊線錘對鋼柱進行校正,用墊板對出現(xiàn)歪斜的鋼柱進行校正;用水平儀對鋼梁進行校正,然后用千斤頂和倒鏈進行校正。
5. Correct the hoisting structure, use the plumb bob to correct the steel column, and use the base plate to correct the skewed steel column; Calibrate the steel beam with a level gauge, and then calibrate with a jack and chain fall.
 
6、施工,操作者必須戴帽,系好繩,同時需要指揮員指揮吊裝。
6. For construction safety, the operator must wear safety helmet and fasten safety rope. At the same time, the safety commander is required to command the hoisting.